Looking at the poor monsoon rains, rising demand and close to stagnant electricity production, Nepal Electricity Authority (NEA) projected that without immediate remedial measures load-shedding during winter could reach as high as 20 hours per day.
Prime Minister Baburam Bhattarai convened a meeting of stakeholders and asked them to limit load-shedding to 12 hours like last year. The Ministry of Energy (MoE) then floated a proposal whose immediate implementation would help the government reach its target. The plan includes construction of a 15 km transmission line to carry electricity from India during winter, operation of multi-fuel plants in Duhabi and Hetauda, construction of the Khimti-Dhalkebar transmission line, reduction of leakages, purchase of additional electricity from India, and expediting work in hydro projects.
However, as it stands now, the reality is that load-shedding will definitely go beyond 12 hours. There are no quick fixes to our power crisis unless production catches up with soaring demand. Meantime, as in previous years, hours of darkness will continue to erode the competitiveness of Nepali goods and services, weaken the industrial sector, widen trade deficit, and jeopardise fiscal balance.
Currently, electricity demand during peak time is around 1000MW, but supply is barely 700MW during summer and 400MW during winter, which includes total NEA production from hydro and thermal, purchase from the private sector, and import from India.
Of the total availability, NEA supplies 55 per cent (including both hydro and thermal), private sector contributes 27 per cent, and 18 per cent is imported from India.
As a result of increase in purchasing power boosted by remittances, trading services are booming. Furthermore, new consumers, which doubled between 2005 and 2011, seeking electricity from the grid are also increasing annually. While demand increases by around 100MW every year, electricity production is moving at a snail's pace.
First, due to the inadequate supply of electricity, firms will be forced to depend on petroleum products (especially diesel, which carries the most weight in NOC's losses and whose consumption more than doubled between 2007-08 and 2010-11) to power up their factories and offices. This will increase the cost of production and erode competitiveness of Nepali goods and services. Since cost of domestically produced goods might be higher than the cost of imported goods of similar nature, industrial activities may continue to further slowdown. Besides, power generated from diesel run generators can fulfil only 25 per cent of total electricity demanded by firms.