Nepal needs to urgently upgrade its aviation gateway. Year after year, Kathmandu's airport has had the dubious distinction of being voted among the top ten worst in the world. Cosmetic improvements have been made lately, but the country's only international airport is plagued with mismanagement and is a known den for smugglers, traffickers and extortionists.
A $100 million ADB-funded project to increase the airport’s capacity has been mired in corruption. Even the modest first phase to expand the present terminal is five years behind schedule because of a dispute between the Spanish contractor and the government.
The only runway is a wreck, operations are frequently halted at peak hour to patch potholes, leading to delays and cancellations. Despite such shoddy and inadequate infrastructure, Kathmandu has the highest landing and ground handling fees in the world, and the most expensive aviation fuel.
Increase in traffic has led to monstrous congestion at both the arrival and departure concourses. Matters become much worse in winter when poor visibility due to proximity to a highly polluted urban core delays flights. Planes are put on hold in the air for hours.
The pressure on Kathmandu was supposed to ease with the construction of two other international airports at Bhairawa and Pokhara. Bhairawa is supposed to serve as a direct gateway to Lumbini, and will have a new terminal building and longer runway to accommodate larger jets. But the $70 million ADB project is delayed because the sub-contractors were conmen. It will now be completed in 2020.
The saga of Pokhara’s new international airport spans four decades. It finally got a go-ahead with a loan from China Exim Bank, but the final inflated price tag of $305 million is suspicously high, and has a whiff of kickbacks in high places.
All these delays have convinced many in government and business of the urgent need of a mega airport in Nijgad in the plains 75km south of Kathmandu. A detailed design by the Korean Landmark Worldwide company envisages two parallel runways 3,600m long, world-class terminal building, aprons, hangars and even an adjoining aeropolis. Tourism Minister Rabindra Adhikari calls it a “game changer”.
Read also: Economy & ecology of Nijgad airport, Om Astha Rai
Up to 2.4 million trees would be cut to accommodate the 80 sq km airport. London’s Heathrow is only 12.14 sq km. Most of the site is covered in dense jungle, the last remaining primary forest in the eastern Tarai and an important corridor for wildlife migration. The government has promised to plant 25 trees for every one cut, and resettle the 7,000 people who will be displaced, but few believe that.
Although the ecological rationale has caught the people’s attention, the much more convincing argument against Nijgad is actually economic. As a Nepali Times investigation in June showed, there are serious questions about the viability of such a gargantuan airport.