Bikash Thapa in Annapurna Post, 24 December
Just as the much-delayed Melamchi water supply project neared completion with 90% of its tunnel construction complete, it is once more in limbo. Every politician in the past few years has been promising the citizens of Kathmandu Valley adequate water supply from the project. The deadline has been pushed back repeatedly for the last 30 years, and the latest official completion date was mid-February 2019.
The Italian contractor had asked for Rs 1.61 billion compensation for delays caused by the earthquake and Indian Blockade in 2015. A Dispute Resolution Board decided in October to award the contractor Rs 350 million, and to pay the amount by 16 November. But when the money did not materialise, the contractor said it could not continue the work and wrote a letter to the ministry saying it was withdrawing from the project.
The talk in the ministry is that Secretary of the Water Supply Ministry Gajendra Thakur and Surya Raj Kandel of the Melamchi Project were ‘bargaining’ with the contractor for kickbacks. Secretary Thakur has a reputation for even forcing subordinates in every ministry he has worked in to pay up to be evaluated positively. The contractor refused to fork out any kickback. Thakur and Kandel then retaliated by refusing to sanction the compensation payment.