Twenty years ago this week, a new Chinese contractor was hired to work on the Melamchi project, and we wrote then that when completed in 2010, the $500 million water supply project would bring 170 million litres of snowmelt to Kathmandu through a 26km tunnel. It took till 2021 to complete, and cost $300million more. A flash flood nearly destroyed the project, and this week its water mains burst in Kathmandu, flooding the central administrative district.
Excerpts of the report published on issue #234 11 – 17 February 2005:
The much-delayed Melamchi project designed to boost Kathmandu Valley's drinking water supply is set to roll again with the appointment of a new Chinese contractor.
The project had faced uncertainty and delay ever since the Korean contractor, Haniel Koneko demanded cost over-runs due to Maoist threats and walked out without finishing even five percent of the work on the access road. Koneko was demanding Rs 100 million extra as compensation while its bid amount was Rs 450 million.